Lunar New Year is 11 days earlier this year. Look ahead and be prepared to keep your supply chain flowing as you need it to.
Although the official break lasts 9 days, many factories close earlier and take longer to return to normal.
This will create pressure
The shorter preparation window means factories will receive a rush of orders earlier than usual.
During January we are likely to see:
- Factories filling their production schedules quickly
- Fewer trucks available to take containers to port
- Shipping space becoming tighter
- Freight rates coming under upward pressure
- More risk of cargo missing vessel cut-offs
- Shipping lines cancelling some departures during and after the holiday
- Slower production during late February while factories rebuild their workforce.
In simple terms, lots of businesses will be trying to move their goods at the same time. Those who leave it late may find their cargo has to wait until after the holiday.
Our advice for UK importers
- Place purchase orders 2–3 weeks earlier than normal.
- Ask suppliers now for their final production and closing dates.
- Aim to have important cargo ready between 10–15 Jan.
- Book ocean freight 3–4 weeks before the planned sailing departure if at all possible.
- Add an extra 1–2 weeks to delivery plans as a buffer.
- Hold additional UK stock where running out would affect your customers.
- Avoid relying on the very last sailing before the holiday.
The good news is that this disruption is predictable. Importers that plan ahead should still be able to secure factory time, container space and sensible shipping costs.
veebox will work with customers to identify their final safe shipping dates, secure suitable departures and reduce the risk of cargo becoming stuck in China during the shutdown.